OPERATIONS GUIDE / LINE RECOVERY

Recover the Production Constraint.

A constrained UAV line should be managed through accepted-output data, constraint identification, containment, root-cause work, and evidence-based recovery gates. Moving work helps only when it addresses the controlling constraint.

What is a constrained-line recovery?

Line recovery is the controlled return from unstable or insufficient accepted output to a defined production basis. It separates immediate containment from permanent corrective action and makes the next rate dependent on evidence.

The visible symptom may be missed deliveries, but the controlling constraint may sit in material, supplier quality, kitting, tooling, work instructions, labor, inspection, test, rework, configuration, planning, or release. Adding work upstream can make the real bottleneck worse.

Recovery sequence

  1. 01

    Protect accepted output

    Define the product state, delivery priorities, material status, quality holds, work in process, test queue, and release condition.

    Output: current-state containment board
  2. 02

    Find the controlling constraint

    Measure flow from material availability through accepted release. Distinguish the bottleneck from downstream symptoms and reporting noise.

    Output: constraint statement and evidence
  3. 03

    Stabilize the process

    Close the highest-impact package, source, process, training, inspection, test, or release gaps at the current controlled rate.

    Output: stable baseline and open-risk list
  4. 04

    Prove recovery gates

    Increase output only after the prior gate demonstrates accepted units, complete records, controlled defects, and support for the next step.

    Output: recovery curve with release evidence

Common symptoms and the questions behind them

A symptom does not establish the root constraint.
Visible symptomPossible controlling issueEvidence to inspect
Assemblies wait for partsMaterial planning, source performance, incoming quality, or effectivity mismatchShortage aging, supplier status, receipt quality, and configuration demand
Work in process keeps growingLine imbalance, inspection queue, test constraint, or release delayQueue by operation, cycle time, first-pass yield, and hold reason
More labor does not raise outputTooling, training, material, instructions, supervision, or downstream constraintWork content, qualification, availability, and accepted output
Test failures increaseProduct variation, process drift, test asset, software, data review, or false failureFailure modes, retest, asset status, configuration, and corrective action
Schedule changes dailyUnstable demand, shortages, priority conflict, data latency, or uncontrolled reworkFrozen window, release inputs, queue health, and exception decisions

When should work move to another production path?

Move work when a complete boundary can relieve the controlling constraint or protect a delivery obligation without creating greater configuration, quality, test, or release risk. A transferable package needs defined inputs, process, tooling, inspection, test, output evidence, and authority.

Do not move work only because another floor appears open. If material is unavailable, test is saturated, or the product baseline is unstable, duplicating assembly may not improve accepted output.

What belongs on a recovery dashboard?

  • Required and accepted output by period
  • Work in process and queue age by operation
  • Material shortages and expected resolution
  • First-pass yield, rework, and top defect modes
  • Inspection and test capacity, availability, and queue
  • Configuration holds and documentation gaps
  • Corrective actions, owner, due state, and verification
  • Evidence required to release the next rate gate

The dashboard should make constraints and decisions visible. It should not be used as a marketing meter or a substitute for source records.